The Student News Site of Colorado State University

The Rocky Mountain Collegian

The Student News Site of Colorado State University

The Rocky Mountain Collegian

The Student News Site of Colorado State University

The Rocky Mountain Collegian

Print Edition
Letter to the editor submissions
Have a strong opinion about something happening on campus or in Fort Collins? Want to respond to an article written on The Collegian? Write a Letter to the Editor by following the guidelines here.
Follow Us on Twitter
Cutting Edge Online Payment Technologies in 2024
April 16, 2024

Businesses worldwide are quickly embracing advanced payment methods to stay ahead in the tight market competition. These methods not only...

Construction approval process ensures optimal campus buildings

Everything’s easier when donors are willing to pay for new buildings.

The capital design and construction approval process were organized for larger construction projects around two years ago by Lynn Johnson, Vice President for University operations, in order to ensure that every idea students, faculty and staff around campus were heard. The approval process includes creating a design, approval from University committees and finding a source of funding.

Ad

“When I moved into this role, I got the sense that there was not as much process wrapped around how we went about approving our buildings,” Johnson said. “We were in a situation where program plans were sitting on shelves not really anything happening to them, and I wanted to make sure that if we were going to take staff time and the resources necessary to do a program plan, we’re going to be doing it on projects that we know are going to be going somewhere.” 

After a conceptual design and budget are worked through with facilities, the plan is presented to the master plan committee, who think about the campus in its entirety when considering additions, and the space committee, who focuses on what actually goes inside the building. Overall, the committees try to ensure that the location, size and presentation of the new buildings make sense and are up to CSU standards, Johnson said.

“We also have been extremely intentional when it comes to the academic spine,” Johnson said. “We’re not going to be putting res halls, auxiliary related, student services for the most part, along with the academic spine unless it’s something that matches up well with where the Lory Student Center is at.”

Although the financial support for the new buildings comes later in the proposal approval process, the proposal group also has to have a plan for funding the renovations. 

Funding for renovations and new buildings come from multiple places, and sometimes larger projects have multiple sources for funding. Funding can come from the state, donors, general funds like tuition and capital request processes, auxiliary revenue for non-academic buildings and the student facility fee.

“If we’re good with their funding sources, then we give them the green light to take it to the president’s operation committee for initial approval, and once they get that approval, they can go forward into the program plan,” Johnson said. “They have to come back through those committees, all of them … because in that process things change, and they need to get back to the Master Planning and Space Committee and OC and make sure that in fact, everything is still copasetic and they’ve got their funding.”

Capital Design and Construction Approval Process:

1. Facilities management development of conceptual scope and budget
2. Facilities management conceptual design
3. Master Plan Committee and Space Committee recommendations
4. Facilities Management cost validation and schedule
5. Plan of financing review
6. President’s Operations Committee for inital approval
7. Program plan and RFP development
8. President’s Operations Committee for final approval

How the student facility fee is used is determined by a board of students called the University Facility Fee Advisory Board. The projects that UFFAB look at are generally under $2 million, like renovating classrooms or attributes to buildings, and those projects won’t have to go through the capital design and construction approval process. UFFAB can also contribute an amount under $2 million to larger projects if deemed beneficial to students.

The board is a way for students to impact the state of the University in the long run, said Nick Bohn, a senior business major and vice chair for UFFAB.

“UFFAB is honestly one of the most unique opportunities that students have in the entire country,” Bohn said. “It’s a super cool opportunity to be on the board and be a part of the conversations, the discussions and all of the planning, and be able to vote on what you think would have the most impact for students.”

Ad

Although students have shown a lot of interest in the renovation of the Andrew G. Clark building, it’s not the next building on the docket, Johnson said. 

The Andrew G. Clark building is structurally sound and there are no safety issues, Johnson said. Currently, there are other buildings that need more attention due to safety concerns and while one building is being renovated, the other buildings are needed to accommodate the decreased number of classrooms.

“There’s this whole domino effect with planning,” Johnson said. “We’re trying to be mindful and intentional about what we need to be doing for the University not just today, but 10 to 15 years down the road.”

Editor’s note: In a previous version of the article “Construction approval process ensures optimal campus buildings” published on Nov. 13 it incorrectly implied that CSU prioritizes which buildings are renovated first. What projects end up being funded and when is dependent on available resources, not a University list. We have clarified this issue. 

Collegian reporter Julia Trowbridge can be reached at news@collegian.com or on twitter @chapin_jules.

Leave a Comment
More to Discover

Comments (0)

When commenting on The Collegian’s website, please be respectful of others and their viewpoints. The Collegian reviews all comments and reserves the right to reject comments from the website. Comments including any of the following will not be accepted. 1. No language attacking a protected group, including slurs or other profane language directed at a person’s race, religion, gender, sexual orientation, social class, age, physical or mental disability, ethnicity or nationality. 2. No factually inaccurate information, including misleading statements or incorrect data. 3. No abusive language or harassment of Collegian writers, editors or other commenters. 4. No threatening language that includes but is not limited to language inciting violence against an individual or group of people. 5. No links.
All The Rocky Mountain Collegian Picks Reader Picks Sort: Newest

Your email address will not be published. Required fields are marked *